RAID log: what it is, a filled-in log and a free template
A RAID log is one list of the four things that sink projects: Risks that might happen, Assumptions you are counting on, Issues that already happened, and Dependencies on people or teams outside your control. Each entry gets an owner and a next step, and the list is reviewed every week.
What a RAID log is
RAID stands for Risks, Assumptions, Issues and Dependencies. The log puts all four in one document because they turn into each other: an assumption that turns out false becomes an issue, a dependency that runs late becomes a risk, a risk that happens becomes an issue.
| Letter | Meaning, with a line from a real log |
|---|---|
| Risk | Something that might happen and would affect the project, usually for the worse. “If the export isn’t ready, finance can’t send the first invoices.” |
| Assumption | Something you are treating as true without proof. “Large accounts are under 50,000 rows.” |
| Issue | A problem that is happening now. “Refunds fail when the webhook times out.” |
| Dependency | Something you need from outside the team, with a date. “Finance confirms how EU tax shows on the yearly price.” |
Many teams read RAID as Risks, Actions, Issues, Decisions. That works too, as long as the whole team uses the same meaning. If decisions matter to you, keep them in their own decision log; they need more detail than a RAID row gives them.
The RAID log template
Four tables in one document, or four tabs in a spreadsheet. Number every entry, so you can say “R-3 just became I-4”.
RAID log: [project] Owner: [name] Reviewed: [every week, at the team sync] Last review: [date] RISKS (may happen) | ID | Risk | Likelihood (L/M/H) | Impact (L/M/H) | What we're doing | Owner | Review by | | R-1 | [If X, then Y] | | | | | | ASSUMPTIONS (we believe this, but haven't checked) | ID | Assumption | If it's wrong... | How we'll check | Owner | Check by | | A-1 | | | | | | ISSUES (happening now) | ID | Issue | Impact | Next step | Owner | Due | | I-1 | | | | | | DEPENDENCIES (waiting on someone outside the team) | ID | We need | From (team/person) | By | Status (on track / late / at risk) | Owner | | D-1 | | | | | | Closed items: move them to the bottom with the date and how they closed.
Let your AI agent fill it in. The free raid-log skill for Claude and Codex keeps this log from your weekly notes, each risk with an owner.
A filled-in RAID log
Here is the RAID log of Tablelight’s launch, two weeks before release, kept by the product manager Maya Okafor.
Risks
| ID | Risk | L | I | What we’re doing | Owner |
|---|---|---|---|---|---|
| R-1 | If the billing export isn’t ready by Nov 24, finance exports the first invoices by hand. | M | H | Sam on the streaming rewrite full time; manual export written up as plan B | Sam Whitfield |
| R-2 | If the annual plan adds work to the pricing page, the page misses launch. | L | M | Yearly toggle ships without a savings badge | Daniel Reyes |
Assumptions
| ID | Assumption | If it’s wrong | How we’ll check | Owner |
|---|---|---|---|---|
| A-1 | Three refund retries catch most timeouts. | Support gets a flood of failed refunds | Count retries in the first week of launch | Priya Nair |
| A-2 | Support can answer billing questions at launch. | Slow answers, angry first customers | Dry run with two support agents on Nov 25 | Maya Okafor |
Issues
| ID | Issue | Impact | Next step | Owner |
|---|---|---|---|---|
| I-1 | Support can’t see failed payments. | Every failed payment becomes a question to engineering | Failed payments log for support (task created, no date yet) | Sam Whitfield |
| I-2 | The invite link expires too early. | New team members can’t join | Task created; needs an owner at Monday’s sync | Maya Okafor |
Dependencies
| ID | We need | From | By | Status |
|---|---|---|---|---|
| D-1 | How EU tax shows on the yearly price | Finance | Nov 18 | At risk: no answer yet |
| D-2 | Product screenshots for the pricing page | Design | Nov 16 | Done |
Two entries tell the story of the week: R-1 has already slipped twice, so its likelihood should go up at the next review, and I-2 has no owner, which is why it’s on the agenda.
How to run the weekly RAID review
- Issues first. They are happening now. For each: is the next step done, and is the owner still right?
- Dependencies with a date this week or next. If one is late, it becomes a risk or an issue today, not at the deadline.
- Risks with high impact. Has the likelihood changed? Did any happen? Move those to issues.
- Assumptions due for a check. Checked and true: close. Checked and false: it’s an issue now.
- Anything new since last week, then close what’s resolved, with the date.
In our experience, ten minutes in the regular team sync is enough. A separate RAID meeting is easy to skip, and then the log goes stale.
RAID log vs risk register vs issue log
| Document | What it covers |
|---|---|
| Risk register | Only risks, often with numeric scores and a formal owner. Common in large programs and regulated projects. |
| Issue log | Only problems happening now, often tracked as tickets. |
| RAID log | All four in one place, lighter than a formal register. Fits most product and project teams. |
Tips that keep a RAID log useful
- Write risks as “if … then …”. “Export” is not a risk. “If the export isn’t ready by the 24th, finance invoices by hand” is.
- One owner per entry, and a date for the next look. An entry without a date never gets looked at.
- Keep it short. Twenty open entries is a lot for one team. If the log grows past that, half of them are noise or belong to another team.
- Link entries to tasks. An issue with a next step should have a task in the tracker, and the task should point back to the log.
- Show the top three in the status report. The status report is where the RAID log reaches the people who can help.
Find the issues before the weekly review.
Numal lines up what stalled since your last sync: a date that slid twice, a task nobody took, a question still waiting on someone, with the question worth asking for each. Those are the rows a RAID log is usually missing until it’s too late.
See how the Sync agenda works- Free for one manager on one board
- No card needed
Questions
What does RAID stand for?
Risks, Assumptions, Issues and Dependencies. Many teams use Actions instead of Assumptions and Decisions instead of Dependencies; write your meaning at the top of the log.
What is the difference between a risk and an issue?
A risk might happen in the future; an issue is happening now. When a risk happens, move it to issues and give it a next step.
Who owns the RAID log?
The project or program manager keeps it. Each entry has its own owner, who is responsible for the next step on that entry.
How often should a RAID log be updated?
Review it weekly, usually in the regular team sync, and add entries as soon as they come up. A log reviewed monthly is out of date most of the time.
Is a RAID log only for big projects?
No. A small team can keep one as a page with four short lists. The value comes from writing risks and dependencies down early, not from the size of the project.
Sources
Keep reading
- TemplateProject status report templateA one-page weekly status: overall state, what moved, what slid, what’s at risk, what you need. With a filled-in report.
- TemplateDecision log templateA running record of what the team decided, who decided it and why, with the five rules that keep it true.
- TemplateAction items template and trackerOwner, due date, status and where it came from: a template and a running tracker for meeting action items.
- GuideMeeting cadenceHow often a team should meet, which meetings earn their place, and a weekly rhythm for a product team.