Numal

Project status report: a free template and a filled-in weekly report

A project status report tells the people above and around a project where it stands: on track or not, what moved since last time, what slid, what’s at risk, and what you need from them. The best ones fit on one page and lead with the one thing the reader must know.

What a status report is for

A status report exists so that people who aren’t in the project every day don’t have to ask. A sponsor, a head of department or a client reads it in two minutes and knows whether to worry, and what you need from them.

That means the reader decides what goes in. They don’t need a list of everything the team did. They need to know if the plan still holds, what changed, and where they can help.

The project status report template

One page, the same sections every week. Paste it into an email, a doc or a page in your wiki.

Project status report templatePlain text. Paste it into Google Docs, Notion, Confluence or a task.
Project: [name]                     Report for: [week of Month D]
Owner: [name]                       Next report: [date]

OVERALL: [On track / At risk / Off track]
[One sentence: why, and what would change it]

Milestones
| Milestone        | Planned    | Now        | Status    |
| [milestone]      | [date]     | [date]     | [on track / moved / done] |
| [milestone]      | [date]     | [date]     | [...]     |

Done since last report
- [result, not activity]
- [result]

Changed since last report
- [date that moved: from → to, and why]
- [scope added or removed, and who decided]

Risks and issues
- [risk]: [impact if it happens] · [what we're doing] · [owner]

Needs from you
- [decision or help needed], from [name], by [date]

Next week
- [the two or three things that must happen]

Let your AI agent fill it in. The free status-report skill for Claude and Codex writes this report every Friday from your project’s records.

Get the skill
SectionWhat to write
Overall statusOn track, at risk or off track, with the reason in one sentence. If you use colors, define them once: “at risk” means a milestone may move unless something changes.
MilestonesThe few dates people care about, planned against now. The “now” column is where bad news shows up honestly.
DoneResults, not activity. “Pricing page live” rather than “worked on pricing page”.
ChangedDates that moved and scope that grew or shrank, with who decided. Leave it out, and readers can’t tell a date that moved from one that never did.
Risks and issuesA risk may happen; an issue already has. For each: the impact, what you’re doing about it, and who owns it.
Needs from youDecisions and help, each with a name and a date. If this is empty for a month, ask whether the report has the right reader.

A filled-in weekly status report

Here is the report Maya Okafor, a product manager at Tablelight, sent to Grace Holloway, the CEO, the week before the launch.

Launch: status for the week of November 16

Owner: Maya Okafor · Next report: November 23

Overall: at risk

Launch date holds, but the billing export slipped a second time and finance needs it for the first invoices.

Milestones

MilestonePlannedNowStatus
Pricing page liveNov 17Nov 17Done
Annual plan ready(new)Nov 20Added this week
Billing export for large accountsNov 16Nov 24Moved twice
Public launchNov 30Nov 30On track

Done

  • Pricing page is live with monthly plans.
  • Team invites shipped.

Changed

  • Annual plan with two months free is in for launch (decided Nov 16 by Maya, replaces “monthly only”). Adds a yearly toggle to the pricing page.
  • Billing export moved from Nov 16 to Nov 24: the streaming rewrite needs two more days.

Risks and issues

  • Export not ready for the first invoices: finance would export by hand for one week · Sam is on it full time · owner: Sam Whitfield.
  • Support can’t see failed payments yet: a log for support is planned, no date · owner: Sam Whitfield.

Needs from you

  • OK to hold the price at $29 until the board meeting, from Grace, by Thursday.

How to write it in 15 minutes

A status report often takes an afternoon because the writer has to collect the status first: open every board, read the comments, message three people. Then the report is late, and the reader has already asked in the channel.

  1. Keep the milestones table from last week and only update the “now” column.
  2. List what changed, not what happened. Go through the tracker filtered to “updated this week”: finished tasks, due dates that moved, new tasks added to the project.
  3. Look for the quiet ones. A task that hasn’t moved in five days is often the real risk, and it never shows up in a list of updates.
  4. Write the overall status last, once you’ve seen everything, and then put it first.
  5. Send it at the same time every week. A report that arrives on schedule gets read; one that arrives “when it’s ready” gets replaced by a meeting.

Mistakes that make status reports useless

  • Green until it’s red. A project that was “on track” for six weeks and “off track” on the seventh wasn’t reported honestly. Use “at risk” early; it’s what the category is for. In one study of 56 experienced software project managers, reports were biased 60% of the time, mostly toward good news.
  • Activity instead of results. “Held three meetings about the export” tells the reader nothing about the export.
  • No “changed” section. Without it, a date that moved twice looks like a date that never moved.
  • No ask. If you need a decision and it isn’t in the report with a name and a date, you won’t get it.
  • A different format every week. Readers learn where to look. Don’t make them relearn.

Get what changed on the board, every morning.

Numal reads your board once a day and sends one short brief: what was done, what was added, which dates changed and what has gone quiet. The “done” and “changed” parts of your status report are already written by the end of the week. For project managers with several boards, a weekly status draft is in early access.

See the Project portfolio assistant

  • Free for one manager on one board
  • No card needed

Questions

What should a project status report include?

The overall status with a reason, milestones planned against now, what was done, what changed, risks and issues, what you need from the reader, and what comes next.

How often should project status reports be sent?

Weekly works for most projects, on the same day each week. Monthly for long, slow programs; daily only in the last days before a launch or during an incident.

What is the difference between a status report and a progress report?

They’re often used to mean the same thing. When they differ, a progress report focuses on work done against the plan, and a status report on where the project stands overall, including risks and asks.

What do red, amber and green mean in a status report?

Green: on track. Amber (at risk): a milestone may move unless something changes. Red (off track): a milestone will move, or already has. Teams define these differently, so write yours down once and use them the same way every week.

Who is a project status report for?

The people who aren’t in the project daily but need to know where it stands: sponsors, managers, other teams that depend on it, and sometimes clients. Write for them, not for the team.

Sources

Keep reading